Clearwater Executive Airport Terminal Replacement Project

  • Project typeReplacement
  • Project cost$ 4.3 Million
  • Project scheduleConstruction began in June 2026, and the Airpark Terminal is expected to open in August 2027 .
  • Contractor nameAmerican Infrastructure Development, Inc. and Bandes Construction
4 Exterior Day_edit.png

The city of Clearwater and the Fixed-Base Operator FlyUSA have broken ground on a new Clearwater Executive Airport terminal building. The groundbreaking marked the beginning of construction on a new facility that will replace aging infrastructure and provide a modern, welcoming space for pilots, passengers, tenants, businesses and visitors.

Aerial

1-Aerial_edit.png

Entrance

2-Entry_edit.png

Exterior Angled

3 Exterior Day 02_edit.png

Exterior Daytime

4 Exterior Day_edit.png

Exterior Nighttime

5 Exterior Night_edit.png

Interior Lobby

6 Interior Lobby_edit.png

The funding for the project was made possible through the collaborative efforts of the city of Clearwater, the Florida Department of Transportation, and Fixed-Base Operator FlyUSA. The new terminal was designed by American Infrastructure Development, Inc. and will be constructed by Bandes Construction.

The Clearwater Executive Airport, formerly known as the Clearwater Airpark, is in the heart of Pinellas County. It is an important transportation asset that provides significant economic impact to the community by supporting local businesses, corporate and general aviation, emergency response operations and visitors to the area. The airport sits at an elevation of 71 feet above sea level, making it the only airport in Pinellas County that is not in a flood zone. The new terminal building reflects the city's continued investment in maintaining safe, efficient and high-quality public infrastructure while enhancing the overall customer experience.


Project Timeline 

April 2026:

  • Pre-construction meeting occurred.

June/July 2026: 

  • Temporary office trailers for FlyUSA arrived.
  • Construction begins

August 2027:

  • Expected construction completion 


Project Update 

Upcoming Tasks:

  • Temporary trailer installation and Bandes Construction mobilizes onsite.

Major Tasks Completed: 

  • 100% design completed; Bandes Construction contract approved by City Council March 20, 2026 for $13.66 million. Purchase order issued.

Location

1000 N. Hercules Ave.,  33765  View Map

Google Map