Oct 2021: Design Start
Sept. 2024: Construction Start
October 2026: Substantial Completion (delay due to Helene & Milton, material delivery/fabrication delays and subsequent critical path electrical work)
Future work: Continuing handrail installation, framing, utility work and fuel dock connections