Project Timeline
- Nov. 19, 2020: Council approved a design work order with Wannemacher Jensen and Associates Inc. for $445,869.
- March 7, 2024: Council approved a construction engineering inspection supplemental work order with Wannemacher Jensen Architects Inc. for $47,415, along with a guaranteed maximum price contract of $8,500,702 with construction manager at risk Biltmore Construction Inc.
- March 2024: Project broke ground.
- June 2025: All punch list items completed; certificate of occupancy obtained; IT and traffic light control installations completed. Fire operations transferred to the new station.
- Sept. 2, 2025: Grand opening held.